Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration
No October is not tornado season
Answer:
The attributed reason for the discrepancy is that Conversion tracking is generating duplicate conversions.
My mans this is to long to read ); I got u tho lemme pick
I know you're going to delete my comment but please let it stay.
I have a essay and I need it to be completed and I need to ask a question. If you have a better reason why you need me to explain it, then please reply. IF you can.
Thanks
: )
Read more on Brainly.com - brainly.com/question/15973749#readmore