Answer:
4.428 hours
Step-by-step explanation:
If the learning rate is 0.81, the slope of the learning curve is:

The time it takes to produce the n-th unit is:

If T1 = 8 hours, the time required to produce the seventh unit will be:

It will take roughly 4.428 hours.