Answer:
The risk consequence of both activities is 1.6 months.
Step-by-step explanation:
We can define a randome variable D: total delay time for the project, and calculate its expected value.
This would be the risk consequence of both activities.
The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.
Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

The risk consequence of both activities is 1.6 months.
Subtract 7 from both sides
12 - 7 < n
Simplify 12 - 7 to 5
5 < n
Switch sides
<u>n > 5</u>
7.8583403e + 14 is the answer to ur question
Answer:h5h5h5h
rfwetgerg5g
Step-by-step explanation:5h5h5h5
5h5h5h5hr5h5eh5h5h5h7,lio.iu.i
Answer:
27
Step-by-step explanation:
39+4=43
27, 31, 35, 39, 43