If 6 men finish a piece of work in 8 days, how long will it rake 4 men to
2 answers:
Answer:
6 men finish a piece of work in 8 days
1 men finish a piece of work in 8*6 days
4men will finish a piece of work in 48/4
days
..
which is equal to 12 days
6 men working 8days = 48man days
So if 4men were to do same work then=48/4 =12 days
So it takes 12 days
You might be interested in
Answer:
n-9=13
n=22
Step-by-step explanation:
Answer: 42 units squared
Step-by-step explanation:
3x7=21
3x7=21 divided by 2 = 10.5 + 10.5 = 21 so,
21+21=42
Hope it helps
The answer is 24 cm squared because to find the area of a rectangle you multiply the width by the height. 6 x 4= 24
Step-by-step explanation:
![{y}^{2} - 1 = 80](https://tex.z-dn.net/?f=%20%7By%7D%5E%7B2%7D%20%20%20-%201%20%3D%2080)
![{y}^{2} = 81](https://tex.z-dn.net/?f=%20%7By%7D%5E%7B2%7D%20%20%3D%2081)
![y = ±9](https://tex.z-dn.net/?f=y%20%3D%20%C2%B19)
![\frac{y - 4}{4} = 1](https://tex.z-dn.net/?f=%20%5Cfrac%7By%20-%204%7D%7B4%7D%20%20%3D%201)
![y - 4 = 4](https://tex.z-dn.net/?f=y%20-%204%20%3D%204)
![y = 8](https://tex.z-dn.net/?f=y%20%3D%208)
![\frac{10 - 63}{y} = 1](https://tex.z-dn.net/?f=%20%5Cfrac%7B10%20-%2063%7D%7By%7D%20%20%3D%201)
![10 - 63 = y](https://tex.z-dn.net/?f=10%20-%2063%20%3D%20y)
![- 53 = y](https://tex.z-dn.net/?f=%20-%2053%20%3D%20y)
Answer:
1). Y=4x-2
2). Y= 2x-1
Explanation:
For the first graph
Slope = 4
Y intercept = -2
Y=mx+b
Y= 4x-2
For the second graph
Slope = 2
Y intercept =-1
Y=mx+b
y= 2x-1