If we write all the possible combinations for this problem, 4/16 or 1/4 would be the answer.
BGGG
GBGG
GGBG
GGGB
This is not taking into consideration the specific order of the children. In case the order will be necessary, the Girls need to be labeled differently and permutation formula needs to be used.
I Wii help with some but not all cause I do have online work to do
Answer:
$7.44
Step-by-step explanation:
$4.96/ 2= 2.48
$2.48 X 3 = 7.44
Answer:
Step-by-step explanation:
A few suggestions:
Put the equations in y = mx + b format
create a table. choose some x and plug that in and solve for y
plot those point. connect the dots
Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.