private static String removeFromString(String old, String frag)
{
int i = old.indexOf(frag);
while (i> -1) {
String rest = old.substring(i + frag.length());
System.out.println("rest = " + rest);
old = old.substring(0, i);
System.out.println("rest = " + old);
old = old + rest;
System.out.println("rest = " + old);
i = old.indexOf(frag);
System.out.println("i = "+ i);
}
return old;
}
Here the index of first occurrence is obtained outside the “while loop” and if this loop runs until index value is >-1. It extracts the rest of the characters other than “frag” from the index and all the characters for which the given set of characters are removed.
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
Answer:
Aqueous carbon dioxide, CO2 (aq), reacts with water forming carbonic acid, H2CO3 (aq). Carbonic acid may loose protons to form bicarbonate, HCO3- , and carbonate, CO32-. In this case the proton is liberated to the water, decreasing pH. The complex chemical equilibria are described using two acid equilibrium equations.
PLS MARK AS BRAINLIEST
Answer:
Process - centered technique
Explanation:
Process - centered technique -
It is the method , where the useless or waste data is converted to some useful information , is referred to as process - centered technique .
This conversion process requires some activities , like maintenance/support , implementation , design , analysis and planning .
Hence , from the given information of the question,
The correct option is Process - centered technique .
Answer:
The answer to this question is given below in the explanation section.
Explanation:
The selection sort algorithm step started from 0, and continue till the sorting is done.
The correct answer after selection sort algorithm at the 4th step is:D
[0,1,2,4,8,10].
The complete detail of step by step execution is shown in the attached document file.