In order to complete the series of substitution values from $35 to $45 in increments of $2.50, follow these steps:
- Input $35 in B21.
- Highlight B21 to B26.
- Go to the Home tab.
- Go to the Editing ribbon.
- Click on Fill.
- Click on Series.
- Step Value = 2.50
- Stop Value = 45.
- Click Okay.
<h3>How can you complete a series of Substitution values?</h3>
First input the value you are to start with in the cell you are to start with. In this case that means putting $35 in Cell B21.
Highlight B21 to B26 and then go to the Home tab. Go to the Editing ribbon at the bottom right and click on Fill. Then go to Series and input the step value as 2.50 and the stop value as 45. Click okay and the range will appear.
Find out more on spreadsheet functions at brainly.com/question/1395170.
Answer:
Explanation:
The following program is written in Java. Using the program code from Purchase class in 5.13 I created each one of the fruit objects. Then I set the price for each object using the setPrice method. Then I set the number of each fruit that I intended on buying with the setNumberBought method. Finally, I called each objects getTotalCost method to get the final price of each object which was all added to the totalCost instance variable. This instance variable was printed as the total cost of the bill at the end of the program. My code HIGHLIGHTED BELOW
//Entire code is in text file attached below.
//MY CODE HERE
DecimalFormat df = new DecimalFormat("0.00");
oranges.setPrice(10, 2.99);
oranges.setNumberBought(2*12);
eggs.setPrice(12, 1.69);
eggs.setNumberBought(2*12);
apples.setPrice(3, 1);
apples.setNumberBought(20);
watermelons.setPrice(1, 4.39);
watermelons.setNumberBought(2);
bagels.setPrice(6, 3.50);
bagels.setNumberBought(12);
totalCost = oranges.getTotalCost() + eggs.getTotalCost() + apples.getTotalCost() + watermelons.getTotalCost() + bagels.getTotalCost();
System.out.println("Total Cost: $" + df.format(totalCost));
}
}
Answer:
iooooooooooooooooooooo
Explanation:
ooooooooooooooo
oooo9ooooo9oooooooooo
ooooooooooooooppppooooooooooo
oooooooooooo
ooooooooooooooooooooo
A terminology which best describe Kevin's goal in terms of expansion and contraction as needs change is: A. Scalability.
<h3>What is scalability?</h3>
Scalability can be defined as a measure of the ability of a system to change (expansion or contraction) in performance and cost as a result of changes in demands of application and system processing, especially in a network architecture.
In this context, we can logically deduce that a terminology which best describe Kevin's goal in terms of expansion and contraction as needs change is scalability.
Read more on scalability here: brainly.com/question/14301721
#SPJ1
Complete Question:
Kevin would like to ensure that his software runs on a platform that is able to expand and contract as needs change. Which one of the following terms best describes his goal? A. Scalability B. Elasticity C. Cost effectiveness D. Agility
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.