Answer:
voluntary contribution $97150
Explanation:
data provided:
tax rate: 2.3%
reserve ratio- 8-10%
average payroll = $971,500
Assume voluntary contribution ="X
"
From the information given in the question we have
%
here we have taken max reserve ratio i.e. 10%

= $97150
we know that, from the question present contribution minus benefit is equal to $93,500
hence, extra contribution = 97150 - 93500 = $3650
extra contribution = $3650
Answer:
Equipment is an _asset__ account. It is reported on the _left_ side of the accounting equation and is __increased__ when equipment is purchased
Explanation:
Buying more Equipment is an asset to company in the sense that it helps in boosting the company production output and in turn generating more profit. It is reported on the left side of the company accounting equation. The aggregate equation increases as the number of equipment purchase increases.
Answer:
It will increase the assets,equity and net income but decrease the liabilities
Based on their observations of what actually occurs in the organization, employees demonstrate the enacted values and norms.
Your values are the things you hold dear in terms of how you conduct your life and career. Value indicates the significance of an action or thing in ethics and social sciences. Values include things like money, allegiance, independence, fairness, equality, justice, brotherhood, and friendship. Values include things like money, allegiance, independence, fairness, equality, justice, brotherhood, and friendship. In the social sciences, norms are a key notion. Norms are most frequently described as socially imposed laws or expectations. Norms can be prescriptive (encouraging good behavior, such as "be honest") or proscriptive (forbidding bad behavior, such as "do not cheat").
Learn more about Norms here
brainly.com/question/15706409
#SPJ4
Answer:
c) Adding additional project resources to the project
Explanation:
Falling behind schedule is something that needs to be avoided or dealt with promptly and systematically
Crashing is the technique to use when fast tracking has not saved enough time on the project schedule. You use crashing to save resources to the project for the least cost possible. Anyhow, crashing is expensive because more resources are added to the project.
References:
Dave. “A Step-by-Step Process of Dealing with a Project That Is Falling behind Schedule.” MyClientSpot Blog, 10 Sept. 2015
Monnappa, Avantika. “Project Management Learning Series: Fast Tracking Versus Crashing.” Simplilearn.com, Simplilearn, 27 Sept. 2019,