Answer: changes in project scope
Explanation:
Project scope is the planning of how a particular project will be accomplished, which includes highlighting and properly stating the project goals, documenting the quantity and quality of materials needed, costing, scheduling tasks, and setting deadlines.
In the case above the manager has already started the project which has an existing plan, then realises that some changes had to be made, after obtaining more information and understanding about the project.
Therefore the project scope had to be revised.
<span>The increase in level of service exports all over the world between 1980 and 2010 is extremely high which is about 10 folds. The phenomenon of economic globalization which means trading of goods, information and infrastructure between various countries is a major thing that occurred during this time.</span>
Answer:
C. Responsibility accounting
Explanation:
The correct answer is C.
Responsibility accounting is a concept of accounting that is used as performance measurement. The main idea is that big and varied organizations are difficult, and almost impossible to manage as one segment, therefore they must be cut into parts or separated into parts that can be managed. These parts, are called responsibility centers that include:
1. Cost centers,
2. Revenue centers,
3. profit centers, and
4. investment centers.
This approach gives room for responsibility to be given to the manager in these parts that have the biggest amount of influence over the key elements that are to be managed.
Answer:
Consumers cannot find enough of a popular new toy in stores.
Explanation:
If there is a shortage, there is not enough supply for the demand.