Answer:
2.25 years
Explanation:
Payback calculates the amount of time it takes to recover the amount invested in a project from it cumulative cash flows
Amount recovered in year 1 : $-345,000 + $220,000 = $-125,000
Amount recovered in year 2 : -1250000 + 100,000 = $-25,000
-25,000 / 100,000 = 0.25
According to McGregor's Theory Y method, a manager might think that workers ought to be involved in both problem-solving and problem-definition.
One of the theories that has a significant impact on both management and employees is McGregor's theory. Additionally, McGregor's descriptions of two different theories, namely Theory X and Theory Y, are further explained below along with each theory's central tenets.
According to Theory Y, a manager's positive perception of their team problem-solving members will increase employee motivation. Managers erroneously McGregor's Theory Y believe that a decentralized approach that strengthens teamwork, collaboration, and trust can address employee demotivation.
Contrary to Theory X, this theory holds that managers do not believe that problem-solving control motivates workers. The team members must be motivated by McGregor's Theory Y meeting their needs for social interaction, self-actualization, and self-esteem.
Learn more about McGregor's Theory Y here
brainly.com/question/28624869
#SPJ4
Answer:
C). information systems existing on different management levels
Explanation: it integrates information across financial management, supply chain management, human resource management, production and design development and so on.
The answer that fits the blank would be PENETRATION. Based on the given scenario above, the penetration pricing strategy was utilized in order for the item that was lowered in price reach a vast part of the market and this would eventually be known to everybody.
Answer:
Appropriate patent amortization expense = $10 million
Explanation:
As per the data given in the question,
Annual amortization expense = Cost ÷ Time
= $36 ÷ 9
= $4 million
Year 2018 Amortization Expense 4 Years = $4 million × 4
= $16 million
Unamortized cost = $36 million - $16 million
= $20 million
Year 2018 Amortization expense 4 years = $20 million ÷ 2
= $10 million