The capital projects fund account for the 10 percent retainage as (B) II only.
<h3>
What is retainage?</h3>
- Retainage is a percentage of the agreed-upon contract price withheld until the work is substantially completed to ensure that the contractor or subcontractor will fulfill its responsibilities and complete a construction project.
- Retention is money kept back by one party in a contract as security for unfinished or defective work.
- Assume the contract is worth $20,000 and you're submitting a paid app after finishing 25% of the work.
- So you earned $5,000 during the pay period, but retainage is 5%. The current progress payment has been reduced by $250.
- As a result, the "Amount Due for this Request" will be $4,750.
So, in the given situation the capital projects fund account for the 10 percent retainage as (II) the credit for $400,000 to Contracts Payable-Retained Percentage, that is (B) II only.
Therefore, the capital projects fund account for the 10 percent retainage as (B) II only.
Know more about retainage here:
brainly.com/question/24101126
#SPJ4
The correct question is given below:
The capital projects fund of Hood River completed the construction of an addition to its city hall at a cost of $4,000,000. The city council approved payment of the amount due to the general contractor, less a 10 percent retainage. How should the capital projects fund account for the 10 percent retainage?
I. As a credit of $400,000 to Deferred Revenue-Retained Percentage
II. As the credit for $400,000 to Contracts Payable-Retained Percentage.
A. I only
B. II only
C. Either I or II
D. Neither I nor II
Answer:
I don't understand what you are asking
Answer:
It will Decreases U.S. real GDP and on the other way round it will increases the well-being of a typical working person in the U.S.
Explanation:
The impact of the decline in working hours is that it will Decreases U.S. real GDP and on the other way round it will definitely lead to increase in the well-being of a typical working person in the U.S. because of the decline in the U.S work week which was formally 60 hours in the 1980 but now 40 hours today because a typical working person will have more time for him/her and the stress involved in working for 60 hours per week will reduce when compared with working for 40 hours per week because a typical working person in the U.S will preferred to work for 40 hours per week than 60hours per week for the betterment of their well being.