Answer:
Reward to risk ratio = (Expected return - Risk free rate) / Beta
Reward to risk ratio of Y = ( 0.145 - 0.056) / 1.2
Reward to risk ratio of Y = 0.089 / 1.2
Reward to risk ratio of Y = 0.0741666
Reward to risk ratio of Y = 7.42%
Reward to risk ratio of Z = (0.093 - 0.056) / 0.7
Reward to risk ratio of Z = 0.037 / 0.7
Reward to risk ratio of Z = 0.0528571
Reward to risk ratio of Z = 5.29%
Security market line (SML) reward-to-risk ratio is the market risk premium itself which is 6.6%.
Stock Y has a reward-to-risk ratio that is higher than the market risk premium, it is currently under-valued in the market. Similarly, since stock Z has a reward-to-risk ratio that is lower than the market risk premium, it is currently over-valued in the market.
Answer:
The correct answer is A.
Explanation:
Giving the following information:
Refurbishing materials:
Variable cost= $600
Fixed costs= $18,800
Estimated cost= 600*35 + 18,800= $39,800
Actual cost= 600*32 + 18,800= $38,000
Refurbishing activity variance= Estimated - actual cost
Refurbishing activity variance= 39,800 - 38,000= 1,800 favorable
Explanation:
They are unlimited/many. Human needs are never restricted, they are infinite and keeps on changing because of various factors. ...
Scarce resources to satisfy them. ...
are recurrent/felt again and again. ...
some are complimentary. ...
change with time age and gender.
Answer:
A. Product APEX
Explanation:
This is the correct answer.
The product of 28 and 97 is 2716