1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
miv72 [106K]
2 years ago
13

Doug is planning to build a model of a sailboat using a scale where 2 inches represents 25 feet. If the sailboat has a sail-heig

ht of 210 feet, what is the length in inches that Doug should build sail-height of the model of the airplane.
Mathematics
1 answer:
Reil [10]2 years ago
3 0

Answer: 16.8

Step-by-step explanation:

2:25 = X:210

210/25 = 8.4

Multiply 8.4 by 2

You might be interested in
Let f(x)=x^2-2x+1
Anarel [89]

Answer:

a.) f'(x) = 2x - 2

b.) horizontal tangent line at (1, 0)

c.) view image

d.) the point given, (-1, -1/2), isn't even located on the graph of f(x). Either there is a typo or the question is poorly stated.

Step-by-step explanation:

a.) You should know how to do derivative already

b.) Horizontal tangent line just mean that the slope is zero. Since a derivative is a slope, just find when the derivative is equal to 0.

c.) The function f(x) looks like a U. The only spot that has a zero slope is at the bottom of the U when the slope changes from negative to positive. Since my horizontal tangent line(where the slope is 0) is located at point (1,0), that must be where the bottom of the graph is,

d.) Poorly stated question. The point given isn't even located on the graph.

3 0
3 years ago
Express 26 as sum of 3 odd primes
vovangra [49]
26 = 1, 3, 9, 13 i added 4 just incase u need sum extra
3 0
3 years ago
7.8+ (x-18)=31 <br>Please Help Asap<br>ty​
lidiya [134]

Answer:

x=41.2

Step-by-step explanation:

hope this helps

8 0
2 years ago
Read 2 more answers
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical pat
ollegr [7]

Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .

Step-by-step explanation:

We assume that this is a normally distribution.

Given : The critical path length is 30 days .

i.e. Population mean = \mu=30

Variance : \sigma^2=25

Then, standard deviation : \sigma=\sqrt{25}=5

Z-score :  z=\dfrac{x-\mu}{\sigma}

The value of z corresponding to 33 = z=\dfrac{33-30}{5}=0.6

Now, the p-value = P(x\leq33)=P(z\leq0.6)=0.7257469\approx0.73

Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.

6 0
2 years ago
Read 2 more answers
What is 5 8/9 + 3 5/12
lukranit [14]

Answer:

9.305 the 5 is repeating

3 0
3 years ago
Read 2 more answers
Other questions:
  • The function h(x)= 12x^8+49 is an even function. Which transformation of h(x) would result in a function that is neither even no
    7·1 answer
  • Can I get an answer to pass my test?
    8·1 answer
  • Demarco wrote two correct variable expressions to represent the phrase “the product of a number and 7.” Which of these variable
    8·1 answer
  • Please help me I will give you the best answer
    9·1 answer
  • 7) In Problem 6 we poured a large and a small bowl of cereal from a box. Suppose the amount of cereal that the manufacturer puts
    7·1 answer
  • Need help please!!! <br> “ALL THE YOUNG DUDES” “CARRY THE NEWSSSS””
    15·1 answer
  • At time t= 0, Elevator A is 40 feet above the ground floor.
    13·1 answer
  • Can someone help me with this
    7·1 answer
  • Х
    13·1 answer
  • −2.4(m−2/3)=−9 <br> Please help! I can't figure it out!
    11·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!