Answer:
Variable cost per unit= $2.27 per machine hour
Explanation:
Giving the following information:
January 3,041 $4,032
February 3,456 $4,608
March 4,147 $6,912
April 5,184 $9,101
May 3,686 $5,760
June 5,322 $9,216
To calculate the unitary variable cost, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (9,216 - 4,032) / (5,322 - 3,041)
Variable cost per unit= $2.27 per machine hour
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer:
B. more than zero if no products were made and would then increase in direct proportion to output
Explanation:
Semi-fixed Cost will be "more than zero if no products were made and would then increase in direct proportion to output."
This is because a semi-fixed cost also known as semi-variable cost or mixed cost is a combination of both a fixed factor and a variable factor.
Such that if production was zero some costs would still be incurred. However, as output rises, the variable part of the costs will rise in direct proportion to output.
Saudi Arabia has the most
Answer:
The correct answer is E)
Explanation:
Capital budgeting is an accounting method that corporations use to decide which planned acquisitions of fixed assets will be approved and which should be refused.
Some examples of Capital Expenditures include:
- Construction of an additional building
- Procurement of delivery vehicles
- Procurement of new equipment
- Rehabilitation of existing equipment
If one of the criteria for classification under Capital Expenditure is that it must be in the plan, then none of the above items mentioned in the question will fly.
Monies have already been expended on the options A, B, and C.
Option D is an offer to purchase an existing asset, not a planned investment. Therefore it also does not qualify.
Hence the correct answer is E.
Cheers!