I’m my opinion this has been the best one in like the pasted two year and also in my opinion the need a country person to sing at halftime.
<span>In theory, Bill can deduct $36000 from his 2016 taxes. However, there are often caps on deductions, so there is really not enough information.</span>
Answer:
$80 lost for not working
Explanation:
Opportunity cost refers to the sacrificed benefits as a result of preferring on a particular option over another. As people make choices, the forfeit one option in favor of another. Opportunity cost is the missed value of the next best alternative.
For John, he has a choice between working or going to the concert. He has two tickets worth $50. Working would mean her twice her regular income, which is $20 per hour. If he works for four hours, his total earning will be $80. If John chooses to go to the concert, he will miss the opportunity to earn $80. The opportunity cost will be the missed $80 that he would have received from working.
Answer:
C-chart is the best suited for this since it is widely used to determine if the defects or returns are within the control limits or not.
Mean = average = 8 per day
Z=3
UcL = mean + 3[square root of mean]= 8+ 3 (Sq root of 8) = 16.48
LcL= mean - 3[ square foot of mean] = - 0.485
So the returns are within the control limits.
Answer:
Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.
Explanation:
activity A =
normal time (NT) = 5 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $500
crash cost per day = [CC - NC]/[CT - NT] = $250/day
activity B:
normal time (NT) = 6 days
Normal cost (NC) = $0
crash time (CT) = 4 days
Crash cost (CC) = $50
crash cost per day = [CC - NC]/[CT - NT] = $25/day
activity C:
normal time (NT) = 8 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $1000
crash cost per day = [CC - NC]/[ CT- NT] = $200/day
The activity that takes the least cost to speed up is the first one to be crashed. from the computations, activity B takes the least cost to speed up, so the project manager should crash activity B first by 2 days.
Therefore, Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.