Answer:
HP PC Hardware Diagnostics UEFI
Explanation:
The 3-in-1 HP PC Hardware Diagnostics UEFI USB Key helps the client distinguish potential software, hardware, and Operating System issues. Both older and newer HP Desktop and Laptop PCs come with this tool installed. By default, it operates outside the OS to detach equipment issues from other system issues. In the event you do not have it pre-installed, you can get it from the official HP site.
Answer:
In a sentence: data is raw numbers, while information is organized data.
Explanation:
Data is a series of numbers or facts. A data set is a collection of data that are related (for examples all the students result in your last math exam). But it's not organized by itself... and rarely mean anything when looked at it in a raw manner.
To make sense of a data collection, you have to analyze it, calculate the mean or median of the data set for example... this is a treatment that has to be done to a data set to give it significance.. after such analysis, the result you have (mean, median, etc..) is a piece of information devired from the data.
Answer:
the CPU utilization decreases as the degree of multiprogramming is increased.
Explanation:
The fundamental concept is that allocating a process with too few frames causes too many and frequent page faults. This implies that the CPU does not perform any useful work and thus its utilization would decrease drastically. In this case, the long-term scheduler, in a bid to improve the utilization of the CPU, would load more processes into the memory so as to increase the extent of multiprogramming. As a result, there would be more decrease in the utilization of the CPU, leading to a chained reaction of higher page faults, which is then followed by a corresponding increase in the multiprogramming degree, usually known as thrashing.
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.