Answer:
"Mesh topology" is the correct answer.
Explanation:
- A mesh topology seems to be a network configuration where there has been an interconnection between each hardware and communications system. This topology configuration allows the distribution of many of these signals, although one of the connexons starts going down.
- This topology needs to connect each destination to any other end destination, thus creating a completely pointless channel.
Answer:
Following are the solution to this question:
Explanation:
The E-government implies use as part of the government systems to offer SMART, which is used to manage smart governance, ethics or accountability, sensitivity, and transparency. It is the research teams, that also shown that policies were progressing in India's creation of information technology. It is also argued against reducing the risk of bribery through improved public official surveillance and reducing its need for citizen engagement with porters with key services.
The below displays ice-creams with its associated flavours. This we would display using <UL>
• Stick
o Chocobar
o Feast
• Bowl
o Butterscotch
o Blueberry
<UL>
<LI>Stick
<UL>
<LI>Chocobar </LI>
<LI> feast</LI>
</UL>
</LI>
<LI>Bowl
<UL>
<LI> Butterscotch </LI>
<LI> Blueberry </LI>
</UL>
</LI>
</UL>
Here <UL> tag is used to create un ordered list and one another <UL> tag inside <LI> created nested list which is the actual requirement. Like this we can created nested unordered lists and you can nest upto 4 levels and increasing the number of levels further may reduce clarity.
Answer:
west ward cpt output
Explanation:
i know because i invented it
Answer:
See explanation below
Explanation:
Previos concepts
First Come First Serve (FCFS) "is an operating system scheduling algorithm that automatically executes queued requests and processes in order of their arrival".
Shortest job next (SJN), or the shortest job first (SJF) or shortest "is a scheduling policy that selects for execution the waiting process with the smallest execution time".
Shortest remaining time (SRF) "is a scheduling method that is a preemptive version of shortest job next scheduling'".
Round robin (RR) is an algorithm where the time parts "are assigned to each process in equal portions and in circular order, handling all processes without priority"
Solution for the problem
Assuming the dataset given on the plot attached.
Part a
For this algorithm the result would be:
Job A 0-6
Job B 6-(6+3) = 6-9
Job C 9-(9+1) = 9-10
Job D 10-(10+4) = 10-14
Part b
For this algorithm the result would be:
Job A 0-6
Job C 6-(6+1) = 6-7
Job B 7-(7+3) = 7-10
Job D 10-(10+4) = 10-14
Part c
For this algorithm the result would be:
Job A 0-1 until 14
Job B 2-(2+3) = 2-5
Job C 3-(3+2) = 3-5
Job D 9-(9+5) = 9-14
Part d
For this algorithm the result would be:
Job A 0-2 , 7-9, 12-14
Job B 2-4, 9-10
Job C 4-(4+1) = 4-5
Job D 5-7, 10-12