Answer:
$3,412
Explanation:
The computation of the economic order quantity is shown below:
=
=
= 2,954 units
The carrying cost is
= $15.40 × 15%
= $2.31
The number of orders would be equal to
= Annual demand ÷ economic order quantity
= 120,000 ÷ 2,954 units
= 40.62 orders
Now The total cost of ordering cost is
Ordering cost = Number of orders × ordering cost per order
= 40.62 orders × $
84
= $3,412
Answer:
The answer is "A"
Explanation:
Cumulative interests are counted by one plus the annual interest rate adjusted to the cumulative periods of less than one. The first principal sum is determined by one. The cumulative sum of the initial loan is then deducted from the calculation.
Formula:

That's why we apply the above formula to calculate the annual interest rate.
Answer:
Project Y = -$1,825.80
Project Z = $4,148.00
Explanation:
Calculation are as attached in the file