The answer base on the given scenario would be letter a,
Roger would gain benefits as he was protected from a financial loss as this
insurance covers him financially as the insurance of which premiums he has paid
and were to gain would only make him the person of having to have the benefit
as he is the one who has the insurance covered for him, which is entitled to
his name and that the benefits and offers would be his gain.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.