Answer:
Part (a) The net income of carter is $115 million.
Part (b) The closing cash balance at the end of year is $360.
Explanation:
Part (a) Net Income Computation:
Sales $825
Cost of goods sold <u>(</u><u>$290</u><u>)</u>
Gross Profit $535
Other Expenses <u>(</u><u>$425</u><u>)</u>
Net income $115 Million
Part (b) The cash balance of Carter is not dependent on non cash flows. So the cash transactions would be considered here for cash balance computation.
Opening Cash position $290
Collection from Sales $710
Inventory Invoices paid ($350)
For Everything <u>($290)</u>
Closing Cash balance $360
Answer: Yes it is
Explanation:
The Permanent Income Hypothesis posits that human expenditure in the short term is based on the amount of income they expect to get as income over the long term.
If a person for instance, knows that they will receive a pay cut at the end of the year, they will probably spend less today to survive the pay cut.
Same goes for the worker in this scenario. They know that the amount they saved is all they have now and into the future so they are adjusting their expenses to ensure they survive on that saving.
Answer:
C. usage rate.
Explanation:
As in the question, it is mentioned that Massage Envy offers massage services based on a subscription basis with a view to targeting the consumers that they get more or multiple treatments per month
So Massage Envy target the market segment via usage rate as it depicts the average sales per day so that they get to know how much they earned the revenue by offering multiple treatments to clients
hence, the correct option is C. usage rate
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186