Answer:
In order to find the present value of the bond we have to calculate the present value of investment A and subtract is from 1529. We can find the present value of A by discounting all its cash flows.
As the first cash flow is received today and the last will be received 3 years form now there will be a total of 4 cash flows
1) 218.19 (Will not be discounted as we are receiving it today in the present)
2) 218.19/1.0987 (Discount by 1 year as cash will be received in 1 year)
3) 218.19/1.0987^2 (Discount by 2 years as cash will be received in 2 years)
4) 218.19/ 1.0987^3 (Discount by 3 years as cash will be received in 3 years)
= 218.19 + 198.58 + 180.74+ 164.51 = 762.02
PV of Bond = 1529-762.09= 766.91
Semi annual coupons mean 2 payments a year. Bond B matures in 23 years which means a total of 46 payments (23*2). N=46. A coupon rate of 6.4 percent means that the bond pays $64 (0.064*1000) each year. $64 divided by 2 is 32 which is the amount of each semi annual payment Arjen receives. Pv= 766.91 FV = 1000
In a financial calculator put
PV= -766.91
N= 46
FV=1000
PMT= 32
and compute I
I is 4.38 and we will multiply it by 2 because the payments are semi annual. So we will get an I of 8.76
YTM= 0.0876
Explanation:
Answer:
Net income will be $160000
So option (c) will be the correct answer
Explanation:
We have given debt common stock = $680000
Credit liabilities = 350000
Credit paid in capital = 190000
And excess of par 30,000 credit Assuming the only changes in retained earnings
So 680000 = 350000+190000+30000+ retained earning
So retained earning = $110000
Dividend paid = $50000
So net income = dividend paid + retained earning = $110000+$50000 = $160000
So option (c) will be the correct answer
Answer:
Answer is the FCAC is greater than the TBC.
Refer below.
Explanation:
A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget. If the cumulative actual cost is greater than the cumulative earned value, then: FCAC is greater than the TBC.
Answer: Ford manufactures a car in Michigan, but uses parts sourced from 27 countries
Explanation:
Globalization is the process by which businesses or organizations develop international influence or a situation whereby they start operating on international scale.
Globalization of production has to do with the producers of final finished goods relocating and moving to other parts of the world in order to source for the necessary raw materials or equipments needed to complete a product and assemble all of them at their facility.
Based on this definition, Ford manufactures a car in Michigan, but uses parts sourced from 27 countries is the right answer.