Answer:
c. No, the new project would have a ROI of 12%
Explanation:
Given that
NOI from new project = $30,000
Investment for a new project = $250,000
Using residual income the Huskie make this investment is shown below:-
Lower than current = NOI from new project ÷ Average operating Assets or Investments
= $30,000 ÷ $250,000
= 12%
No, the new project would have a ROI of 12%
Answer:
Is this one of the people that give free points?
Answer:
(Hope this helps can I pls have brainlist (crown)☺️)
Explanation:
Environmental, Social, and Governance (ESG) is an acronym that stands for Environmental, Social, and Governance. These non-financial aspects are increasingly being used by investors in their analytical process to identify major dangers and growth prospects.
The goal of this research is to use ESG integration to produce new types of competitive advantage, not only ESG ratings. It can't be left exclusively to the investor relations team or the sustainability department since it includes key strategic and operational decisions.
Answer:
Predetermined manufacturing overhead rate= $2.15 per direct labor hour
Explanation:
Giving the following information:
It takes 80,900 direct labor hours to manufacture the X-1 and 93,500 direct labor hours to manufacture the X-2 Line.
Total overhead= 225,000 + 149,960= $374,960
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 374,960 / (80,900 + 93,500)
Predetermined manufacturing overhead rate= $2.15 per direct labor hour