Answer:
Option B
Explanation:
The answer is Option B "an interview." Secondary data is data coming from someone else who isn't the researcher a good example of secondary data would be a interview. A interview the researcher is asking a person for data on the subject and they give their point of view/opinion on it.
Hope this helps.
Answer:
$12 million
Explanation:
Gross domestic product is the total sum of final goods and services produced in an economy within a given period which is usually a year
GDP calculated using the expenditure approach = Consumption spending by households + Investment spending by businesses + Government spending + Net export
contribution to GDP = value of final good - value of intermediate good
14 = 2 = 12
Answer: is Option D. <em>A plane turbine manufacturing company in South Africa</em>
<em />
Explanation:
Discrete manufacturing is the production of distinguishable items that can be decayed back into their basic parts. <u><em>For example</em></u><em>:</em> Automobiles, airplanes, furniture, and toys are the examples of discrete manufacturing products.
For industrial purpose the discrete manufacturing contains production of consumer electronics, appliances, computer and related accessories, as well as many other household items. Production of cars and airplanes also falls under discrete manufacturing products. Discrete manufacturing companies manufactures physical items that go straight to the consumers and businesses.
Increasing at the moment. After a few weeks, when the price becomes unreasonable, I doubt Marvin would want to buy chocolate truffles.
I hope you found this helpful! :)
Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.