Answer:
100
Explanation:
Goal programming is an optimization technique that allows for multiple, normally conflicting objectives and then attempts to solve each goal sequentially to a satisfactory level. In goal programming, differential variables are being used.
Since the goal programming problem had two goals. Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory. The optimal solution to this problem resulted in a profit of $2,300 and no idle time
This means that goal number 2 was achieved since the optimal solution resulted in no idle time. But goal number 1 was not achieved because a profit of $2300 was achieved in the solution instead of $2400.
Therefore, the value for the objective function for this goal programming problem = 2400 - 2300 = 100
Answer:
The answer is option D) In doing "aggregate planning" for a firm producing paint, the aggregate planners would most likely deal with: all the different sizes and all the different colors by size.
Explanation:
Aggregate planning is concerned with forecasting the needs operational needs of an organization and making provisions for them ahead of time.
Aggregate planners develop, analyze, and draft an estimated schedule of the overall operations of an organization.
This estimated schedule contains targeted sales forecasts, production levels, inventory levels, and customer backlogs.
In doing "aggregate planning" for a firm producing paint, the aggregate planners would most likely deal with: all the different sizes and all the different colors by size.
The purpose of aggregate planning is to maximize the utilization of equipment in order to increase productivity levels.
Answer:
Explanation:
Pretax cost of debt is the annual rate(YTM) of the bond. Using a financial calculator, input the following to calculate it;
N = 5*2 = 10
PV = -(95% *10,000,000) = -9,500,000
Coupon PMT = (6%/2)*10,000,000 = 300,000
FV = 10,000,000
then compute semiannual rate; CPT I/Y = 3.604%
convert to annual rate = 3.604*2 = 7.21%(this is the pretax cost of debt)
After tax cost of debt is calculated because interest payable on debt has tax shield. The formula is as follows;
Aftertax cost of debt = pretax cost of debt (1-tax)
AT cost of debt = 7.21% (1-0.40)
AT cost of debt = 4.33%
Thanks you for helping me with the link
Explanation:
The measurement of productivity in service and manufacturing is different in the sense of the ability to measure productivity, as a service has different characteristics that are Intangibility, Inseparability, Variability and Perishability, it is more difficult to measure its productivity, for example, a service is variable, so even if there are standards for the provision of that service, there are issues that will vary and this can change productivity.
There is also the fact that if the productivity measured by the capacity in the service sector is influenced by the loss of quality of the same, as customers may feel hurt if there is a rush in a service provided, for example, so that the service is more productive .