Answer: Crater will be bound because of Borg's apparent authority.
Explanation:
Crater Corp. will be bound to the contract since Bo Borg has the apparent authority as the acting Vice President of purchasing. Even though he went over the agreed amount that was over 2 million in the contract. Since the Shady company was unaware that he had exceeded his authority the contract will stay in place. If Shady company had of known that he did not have the final say and needed approval the result of the transaction would of been different.
Answer:
The economic incentive was to produce enough to meet the output target, without regard for quality or cost.
Explanation:
As the only condition for the payment to the producers is linked with the output thus there is no constraint for the quality and the sales of the product. This indicated that the producer will get the reward irrespective whether the quality or cost of the product is feasible or not.
Answer:
Hire an external consultant to pick new team members for you
Explanation:
On the given scenario there are limited project spaces and plenty of volunteers for those positions.
An equitable and impartial method of choosing team members needs to be used to avoid conflict.
The best solution is to hire an external consultant who can be seen as impartial to do the selection.
This way employees will accept the objectivity of the selection since the external consultant does not have any underlying.interest in who occupies the project positions
Answer:
In situations where customers ask to hold the bookings without any advance payment, they clearly mean to book it but keep other options open. It is highly risky because the customer has no stakes to lose and if he finds a similar product in lower cost or with a better package, they will most definitely change their vendor.
Therefore is is necessary to book products with advance payments so if even the customer backs out, you will not have lost all of your stakes.
The answer for Equivalent units for the period will be calculated as follows under FIFO
1. Units from beginning work in process: calculate this as beginning work in process units x (100% – given % complete) to calculate the amount of additional work needed to make the unit 100% complete.2. Units in progress and completed this period: take the units x 100% complete since they were started and completed they have received all of their materials, labor and overhead and will not receive any more since they are finished.3. Units in Ending work in process: take the ending work in process units x a given % complete.
Solution by step:
Equivalent units = 1. (5,000 × 40%) +2. (31,000 – 5,000) (Since there is a beginning work in process deduct this from the units completed) +3. (2,000 × 80%)
= 2000 + 26000 + 1600
Answer = 29,600 units