Answer: Detailed design
Explanation:
A detail design phase has to do with the completion of the design of the product. The design team works toward the completion of the required specifications for the product, product elements, and its manufacturing processes.
The detail design phase is an iterative process and here, design trade-offs are done as the design team learns about the effect of the design decisions on the reliability, performance, and cost of the product.
Answer:
safety stock = 33 desks
reorder point = 133 desks
Explanation:
safety stock = (Z-score x √lead time x standard deviation of demand) + (Z-score x standard deviation of lead time x average demand)
- Z-score for 98% confidence level = 2.326
- standard deviation of demand = 10
- √lead time = √2 = 1.414
- we are not given any standard deviation of lead time, so we can assume that it is 0
safety stock = (2.326 x 1.414 x 10) + (2.326 x 0 x 50) = 32.89 ≈ 33 desks
reorder point = lead time demand + safety stock = (50 x 2) + 33 = 133
Answer:
B. traditional
Explanation:
There is this term traditional structure which reflects any activity done in its oldest and modest manner.
Basically when an importer imports goods, then he shall hold the entire right to sell those goods further, through a person he wants. When an importer controls the supply, in terms he decides as to what quantity shall be ordered and then be sold through an agent or a proper marketing system, then the distribution structure is said to be traditional.
The correct option is B.