Answer:
The depreciation expense for 2015 is $2,000
Explanation:
The computation of the depreciation expense is shown below:
= (Original cost - residual value) ÷ useful life
= ($35,500 - $4,000) ÷ 7 years
= 4,500
The depreciation for three years would be
= 4,500 × 3 years
= $13,500
The remaining amount would be
= $35,500 - $13,500
= $22,000
So, the depreciation expense for 2015 would be
= ($22,000 - $4,000) ÷ 9 years
= 2,000
Answer:
the scope statement; deliverables
Explanation:
"Decomposing" a project will ensure an efficient way of accomplishing the project's goal. Before doing this, it is important to know what "the scope statement" is and the "deliverables" (multiple tasks in the production).
"The scope statement" allows one to know what should be included in the decomposition. It also tells <em>when you are going to stop breaking down </em>and what tasks are to be included. Once you know this, it<em> becomes easier to decompose a projec</em>t with<u> one deliverable at a time.</u> The scope will also be further clarified.
So, this explains the answer.
Answer:
A) Indirect exporting
Explanation:
An indirect exporting strategy refers to selling to an intermediary business. The intermediary business is responsible for selling and distributing the product in their domestic market.
This is the easiest way of exporting since GHB will only be responsible for delivering the goods to the intermediary, and it will not need invest anything in the country. The intermediary assumes the risks of selling the goods directly to customers or using wholesale distributors.
Answer:
Simple Interest=P*r*n= $20 million * 0.18 * 1= $3.6 million
Therefore amount accumulated= $20 million + $3.6 million = $23.6 million
Amount accumulated through Compound Interest=P×(1+r) ^t
= $20 million( 1+0.18/12)^12= $23.912 million
Explanation:
Simple interest is based on the principal amount of a loan or deposit, while compound interest is based on the principal amount and the interest that accumulates on it in every period.
Answer:
Allocated MOH= $432,000
Explanation:
Giving the following information:
Predetermined overhead rate of $8.00 per machine-hour
Actual machine-hours worked= 54,000 hours
<u>To calculate the allocated overhead, we need to use the following formula:</u>
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 8*54,000
Allocated MOH= $432,000