Answer:
Crash the schedule.
Explanation:
Fast-track can complete the task earlier but takes more money. Assign more experienced people will cost the management more money. Cut scope reduces the project requirement and finishes the task earlier. Therefore, options A B and D can not be the answer.
Crash the schedule (option C) is the answer because it allocates enough resources to complete the task earlier without spending more money.
Answer:
FV= $46,031.45
Explanation:
Giving the following information:
Monthly deposit= $450
Number of months= 59
Interest rate= 0.21/12= 0.0175
To calculate the final value, we need to use the following formula:
FV= {A*[(1+i)^n-1]}/i
A= monthly deposit
FV= {450*[(1.0175^59) - 1]} / 0.0175 + 450
FV= $46,031.45
Answer:
$57.11
Explanation:
$25.85 × 4 = $103.40
$15.70 × 2 = $31.40
Total cost of purchase = $134.80
6% tax = 0.06 × $134.80 = $8.09
Total cost of purchase including tax = $142.89
Change received by Blaine = $200 - $142.89 = $57.11
I hope my answer helps you