Answer:
If closed the operating income will decrease by 50,000
Is a better scenario to continue with the residential sercives
Explanation:
<em><u>current scenario:</u></em>
contribution margin 450,000
Fixed Cost 480,000
net loss 30,000
<em><u>drop scenario:</u></em>
contribution margin = 0
fixed cost 450,000-370,000 = 80,000
net loss (80,000)
Answer:
Price Risk, Reinvestment Risk, Investment Horizon and Longer maturity Bond.
Explanation:
- Price risk is the risk of a decline in a bond's value due to an increase in interest rates. This risk is higher on bonds that have long maturities than on bonds that will mature in the near future.
- Reinvestment risk is the risk that a decline in interest rates will lead to a decline in income from a bond portfolio. This risk is obviously high on callable bonds. It is also high on short-term bonds because the shorter the bond's maturity, the fewer the years before the relatively high old-coupon bonds will be replaced with new low-coupon issues.
- Which type of risk is more relevant to an investor depends on the investor's investment horizon, which is the period of time an investor plans to hold a particular investment.
- Longer maturity bonds have high price risk but low reinvestment risk, while higher coupon bonds have a higher level of reinvestment risk and a lower level of price risk.
I don't really understand your question but it is bad to pay only the minimum towards your credit card, interest rates will keep adding to your bill.
Answer:
a.the reorder point = lead-time demand
Explanation:
The reorder point is when there needs to be a replenishment of depleted stock of inventory.
Lead time is the time between when an order is placed and when delivery of goods and services is made.
So when there is constant demand and fixed lead time, there is no need to keep excess inventory as demand has been anticipated and inventory for the demand is available.
Also the lead time demand from order to delivery is also fixed because demand has been provided for already.
Thus reorder point= lead time demand