Answer:
b.The IRR is equal to 25.85%
Explanation:
Firstly we are given that i consider investing $100000 which will in this problem be our Cinitial which is the initial investment for the project.
Then now given the risk of this project, my cost of capital is 20% so then we will compare this to the IRR and see if i can accept the project or not if the cost of capital is greater than the IRR than its not good to invest on the project but if the cost of capital is less than the IRR then the this will be a good investment as the cost of capital also checks the opportunity cost.
The future payment cash flows which is $500000 so we will use the following formula:
NPV = (cash flow)/(1+IRR)^n - initial investment
so we find the present value of the cash flow of the investment and subract the initial investment which will give us a zero cause the present value of the cash flow is equal to the initial investment therefore( n is the period of cash flows):
0= $500000/(1+IRR)^7 - $100000 transpose the initial investment and solve for IRR.
$100000(1+IRR)^7= $500000 then divide both sides by $100000
(1+IRR)^7 = 5 then find the 7nth root of both sides to eliminate the exponent of 7
1+ IRR = ![\sqrt[7]{5}](https://tex.z-dn.net/?f=%5Csqrt%5B7%5D%7B5%7D)
1+IRR = 1.258498951 then subtract 1 both sides to solve for IRR
IRR = 0.258498... then multiply by 100 as IRR is a percentage
IRR= 25.85 % rounded off to two decimal places which is the answer b
Answer:
Los procesos que intervienen en la formación del relieve son los procesos endógenos y Exógenos. Los procesos endógenos son los procesos que se dan en el interior de la cortesa terrestre, como son el movimiento de las placas tectónicas, los desplazamientos continentales, entre otros.
The appropriate action would be: C. <span>Thank the taxpayer, and explain that you cannot accept any payment for your services.
Government workers couldn't receive cash payment in any kind unless there is a necessary administrative purpose.
They could on the other hand, receives Gifts that held the value less than $ 20</span>
Answer:
$1,069.74
Explanation:
We use the present value formula which is shown in the attachment below:
Data provided in the question
Future value = $1,000
Rate of interest = 12%
NPER = 16 years
PMT = $1,000 × 13% = $130
The formula is shown below:
= -PV(Rate;NPER;PMT;FV;type)
So, after solving this, the value of the bond is $1,069.74
Answer:
Total cost is equal to $81300
So option (c) will be correct answer.
Explanation:
Actual unit of production = 42000
Cost of per equivalent material = $1.10
Equivalent cost of material =
$
Equivalent cost of labor =
$
Therefore total cost of production = $46200+$35100 = $81300
So total cost will be $81300
Therefore option (c) is the correct answer