Answer:
a. estimate the amount to mitigate high impact and probable issues.
Explanation:
In project management, a contractor can be defined as an individual or organization that temporarily undertakes a project in order to create a unique result, product, and service.
A contingency is an amount of money which is added to the initial or standard cost estimate so as to cover risk exposure and any uncertainty.
When making contingency estimates, the contractor should estimate the amount to mitigate high impact and probable issues.
As a result of uncertainties that are peculiar to everything in life, most especially projects undertaken, it is very important and necessary that the contractor should set aside an amount of money to mitigate or lessen any high impact such as dwindling prices, miscellaneous, faults, repairs and other probable issues that may arise in the process of execution.
Answer:
Correct option is C
Explanation:
Increase in \alpha decreases πt - π(t-1) which shows decrease in natural rate of unemployment.
Phillips bend clarifies the connection between expansion rate and joblessness rate. As indicated by it there is a reverse connection between the joblessness rate and swelling rate. It implies there is an exchange off among expansion and joblessness rate.
The strategy ramifications of Phillips bend is that administration can't lessen swelling and joblessness together. It joblessness decreases, at that point the economy must acknowledge higher expansion. Then again, on the off chance that economy lessens expansion, at that point it must acknowledge higher joblessness.
When there is synchronous change in the swelling rate and joblessness rate then this is an instance of development along the short-run Phillips bend.
Then again, when either joblessness rate or swelling rate stays unaltered while different changes then it prompts moving of short-run Phillips bend.
Answer:
1. Per se application - US Competition law
Justification: It is a provision of US competition law
2. Misuse of activity - EU Competition law
Justification: It is a provision of EU competition law
3. Extraterritoriality - US and EU
Justification: It is a provision of US and EU antitrust and competition law
4. Trade obstacle, non-tariff - France
Justification: These are considered to be part of the France trade system
5. Strict liability - U.S. Tort Law
Justification: It is part of the U.S. Tort Law and depends on intent to harm liability
6. Punitive damages - U.S. Product Liability Law
Justification: It is a provision of U.S. Product Liability Law
Answer:
A production function
Explanation:
A production function shows the relationship between the physical quantity output and the input of a good produced. It is the technical relationship between the physical output and physical input of a good. The production function is expressed as a mathematical function that relates inputs in numbers and their effect on output numbers.
Answer:
![\left[\begin{array}{cccccc}&Cost&Assembly&Setting Up&Other&Total\\wages&349,000&226,850&69,800&52,350&349,000\\Depreciation&290,000&101,500&58,000&130,500&290,000&Utilities&199,000&29,850&149,250&19,900&199,000&Total&838,000&358,200&277,050&202,750&838,000&\end{array}\right]](https://tex.z-dn.net/?f=%5Cleft%5B%5Cbegin%7Barray%7D%7Bcccccc%7D%26Cost%26Assembly%26Setting%20Up%26Other%26Total%5C%5Cwages%26349%2C000%26226%2C850%2669%2C800%2652%2C350%26349%2C000%5C%5CDepreciation%26290%2C000%26101%2C500%2658%2C000%26130%2C500%26290%2C000%26Utilities%26199%2C000%2629%2C850%26149%2C250%2619%2C900%26199%2C000%26Total%26838%2C000%26358%2C200%26277%2C050%26202%2C750%26838%2C000%26%5Cend%7Barray%7D%5Cright%5D)
Explanation:
We mulitply each line by the stated percent of each activity
<u>for example</u>
Setting Up % x Utilities= Utilities cost assigned to setting up
199,000x 75% = 149,250
Assembly % Depreciation= Depreciation cost assigned to assembly
35% x 290,000 = 101,500
This process must be done to assign each portion of cost.