Accepting to all races religions genders sexualitys and be willing to protect those with different identities and help prevent discrimination
Answer:
There is low interest rate. There is minimum balance requirement problem. There is federal withdrawal limit.
Explanation:
I think she did because she know the prize is $500.00.
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
$87,000
Explanation:
Calculation of the conversion cost for November.
Conversion cost can be defined as the combination of both direct labor costs and manufacturing overhead costs that are vital to help convert raw materials into product.
Using this formula
Total Conversion cost = Direct labor cost + Manufacturing overhead cost
Hence,
Direct labor cost $25,000
Add Manufacturing overhead cost $62,000
Total Conversion cost $87,000
Therefore the conversion cost for November is $87,000