Answer:
Bob's predetermined overhead rate = 9.91
Explanation:
Calculation for predetermined overhead rate
Predetermined overhead rate = Estimated (Budgeted) Overhead Expense / Estimated Direct Labor Hours
Predetermined overhead rate = 110917 / 11198
Predetermined overhead rate = 110.917 / 11.198
Predetermined overhead rate = 9.91
I think it’s b chapter 10
Answer:
![A = 28000 [\frac{0.12 (1.12)^4}{(1.12)^4 -1}]](https://tex.z-dn.net/?f=%20A%20%3D%2028000%20%5B%5Cfrac%7B0.12%20%281.12%29%5E4%7D%7B%281.12%29%5E4%20-1%7D%5D)
![A = 28000 [\frac{0.12*1.574}{1.574-1}]](https://tex.z-dn.net/?f=%20A%20%3D%2028000%20%5B%5Cfrac%7B0.12%2A1.574%7D%7B1.574-1%7D%5D)

So then the annual pay would be $ 9218.564 for this case
Explanation:
For this question we can use the Equivalent annual value (A) given by the following expression:
![A = PV [\frac{i (1+i)^t}{(1+i)^t -1}]](https://tex.z-dn.net/?f=%20A%20%3D%20PV%20%5B%5Cfrac%7Bi%20%281%2Bi%29%5Et%7D%7B%281%2Bi%29%5Et%20-1%7D%5D)
Where
represent the pesent value
since the rate is yearly
since we have 4 years to pay
So then we have everything to replace and we got:
![A = 28000 [\frac{0.12 (1.12)^4}{(1.12)^4 -1}]](https://tex.z-dn.net/?f=%20A%20%3D%2028000%20%5B%5Cfrac%7B0.12%20%281.12%29%5E4%7D%7B%281.12%29%5E4%20-1%7D%5D)
![A = 28000 [\frac{0.12*1.574}{1.574-1}]](https://tex.z-dn.net/?f=%20A%20%3D%2028000%20%5B%5Cfrac%7B0.12%2A1.574%7D%7B1.574-1%7D%5D)

So then the annual pay would be $ 9218.564 for this case
And this amount would be paid each year in order to pay all the money after 4 years.
Answer:
22.22%
Explanation:
The calculation of percentage in sales is shown below:-
Increase in profit required = $25,000 - $15,000
= $10,000
To achieve a profit $10,000, the required sales increases
= $10000 ÷ 18%
= $55,555.55
Percentage increase in sale = Required sales ÷ Sales of current situation
= $55,555.55 ÷ $250,000
= 22.22%
So, for computing the percentage increase in sales we simply applied the above formula.
Answer:
identify the critical path
Explanation:
Based on the information provided, the logical next step for Emily would be to identify the critical path. This means identifying the sequence of project network activities that add up to the longest overall duration which in term will reveal the shortest time possible to complete this project through unnecessary parts within the critical path, and will allow her to meet the imposed deadline.