Answer:
b. $128,168
Explanation:
Hanung Corp
Service Departments
Maintenance Department Personnel Department
Costs $360,000 $110,000
Cost Driver budgeted maintenance-hours number of employees
Budgeted
Maintenance-hours NA 880
Number of employees 60 NA
Production Departments
Department A Department B
Budgeted Costs $188,000 $282,000
Budgeted
Maintenance-hours 1230 680
Number of employees 290 630
<em>First we find the rate by dividing the total budgeted cost of Maintenance with the budgeted maintenance hours then we multiply it with the maintenance hours of Department to B to get Department B maintenance Costs.</em>
Using the direct method, the amount of Maintenance Department costs will be allocated to Department B
=($ 360,000/ 1230+680 )*680=($ 360,000/ 1910 )*680=$ 128167.53
= $ 128167
So choice B is the correct answer.