Answer:
Common Stock $3,400 (credit)
Mower $1,600 (debit)
Revenue Service $1,000 (credit)
Cash $2,600 (debit)
Gas Expense $100 (debit)
Dividends $0
Explanation:
See below the posting i have done to the ledger accounts.
Mower T - Account
Debit :
Accounts Payable $1,600
Credit :
Balance c/d $1,600
Revenue Service T - Account
Debit :
Balance c/d $1,000
Credit :
Account Receivable $1,000
Cash T - Account
Debit :
Common Stock $3,400
Credit :
Gas Expense $100
Dividends $700
Balance c/d $2,600
Gas Expense T - Account
Debit :
Cash $100
Credit :
Balance c/d $100
Dividends - T Account
Debit :
Shareholders for dividends $700
Credit :
Cash $700
Answer: Option D
Explanation: Internal rate of return ,denoted as IRR, is the rate at which the net present value of a capital investment is zero. It is the rate at which the cash flows of the investment are discounted back to calculate the present value.
While, required rate of return is that return which an investor expects to achieve over time from a capital project.
Thus, one would only select a capital project only if the NPV of a project is positive which can only happen when the return on investment, that is, IRR, is greater than cost of capital, that is, required rate of return.
Answer: 1. statement d
2. statement d
Explanation: This can be explained as follows :-
1.Government intervention should be done on those sectors that results in maximization of wealth. Private sector is the back bone of every economy's free market, thus, protecting private property is the correct option.
.
2. Issuing patent right to the inventor will result in monopoly by that particular producer and that too of a necessary commodity hence option d is correct.
Answer: Resource levelling
Explanation:
Resource levelling is a term used in project management defined and is defined as a technique used where there is adjustment in the start and finish dates based on limitation in resources with the aim of balancing the demand for resources using the available supply.
While performing activities in project planning, the manager will try to schedule some tasks simultaneously. Resource leveling can be used to balance the workload of the main resources during the duration of of the project usually at the expense of either the time, cost or scope.