This system facilitates the establishment by state, Municipality, Militaristic, Provincial and local governments of a detailed, national framework for disaster response. This command structure of each person refers to only a single ICS boss because of NIMS management, and the wrong option can be defined as follows:
- In option A, The Continuous report describes your daily details.
- In option B, These reports are not in one ICS supervisor.
- In option D, It can not assign different competences.
It’s all depending on what method
Answer:
Bike Frame Flow Time
The value-added percentage of the flow time for this bike frame is:
= 46.
Explanation:
a) Data and Calculations:
Bike Frame Flow Time:
Setup time = 7 hours
Processing time = 6 hours
Storage time = 7 hours
Flow time of the bike frame = 13 hours (7 + 6)
Value-added percentage of the flow time for this bike frame = 6/13 * 100
= 46%
b) Flow time represents the amount of time a bicycle frame spends in the manufacturing process from setup to end. It is called the total processing time. Unless there is one path through the process, the flow time equals the length of the longest process path. The storage time is not included in the flow time since it is not a manufacturing process.