Answer:
Information and communications technology (ICT) is an extensional term for information technology (IT) that stresses the role of unified communications[1] and the integration of telecommunications (telephone lines and wireless signals) and computers, as well as necessary enterprise software, middleware, storage and audiovisual systems, that enable users to access, store, transmit, and manipulate information.
D. The word "food" is the most abstract because it is the least specific and does not specify what food it is exactly.
Hope this helps!! :)
Answer:
B. Click the Next icon on the Reviewing toolbar to review and then accept or reject each edit.
Explanation:
Since Jack wants to keep some changes and reject others, he can't use a global solution (like presented in answers A and C).
He has to go through each and every change proposition and decide individually if he wants to keep the change or not. That's why it's answer B.
It's the only way to accept some, reject some.
At the end of this process, he'll have a clean document with Rob's recommendations and his original documents.
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.