Answer:
The correct answer would be, Brainstorming.
Explanation:
Dean used a technique, called Brainstorming.
Brainstorming is a process of generating new and innovative ideas by group discussion.
When a group of people discuss anything and generate ideas or give innovative solutions of the problem being discussed, they are actually resolving the problem and this process is called as brainstorming.
So in this question, when Dean went to his team to seek solution to the problem which he recently encountered, his team came up with surprisingly new innovative ideas that astonished Dean. So Dean actually used a technique called Brainstorming to make his team generate solution for the problem with their ideas and suggestions.
Good treatment for customer,well coming of the customer,to provide quality surviec
<span />
Answer:
Adriana Corporation
Using the High and Low method the Variable and Fixed portions of the Total Cost is:
Fixed Costs = $247,420
Variable Costs = $39.50 Per unit x 8,020 Machine Hours = $316,790
B. at an average of 7,500hrs Machine hours, the estimated Overhead costs = $247,420 x (39.50 x 7,500)
= $543,670
Explanation:
The High and Low Method is a costing method which attempts to split the mix of Fixed and Variable costs in a mixed Total cost of production by looking at one element of variability (in this case Machine Hours)
It is a subjective approach, however simple to calculate. Other method is the regression analysis, which is more complex in comparison to the high and Low
The attached excel file shows how we derived the Variable and Fixed Costs element of the Overhead Costs
djsjsb
cvhjedskjb
gdggd
Answer:D.
Someone is given responsibility for deciding how to meet the need.
Explanation:
Answer:
Stop working and add the incomplete feature back into the backlog.
Explanation:
In case a task could not be completed in the current iteration, it is best to add it to the backlog, so that in subsequent iterations it will be completed (giving it priority, of course).
Of course, it is not convenient to extend the iteration time just to finish the incomplete task. Also, we should not add it directly to the next iteration because we would be altering its structure. So the most appropriate thing to do, is to leave it marked as a priority to be included in the next iterations.