I need help with this it is properties of multiplication and addition

Mathematics
1 answer:
Marat540 [252]3 years ago
3 0

Answer:

Commutative Property

Step-by-step explanation:

Commutative Property states that order doesn't matter for addition.

You might be interested in
Jacob earns $300 per week plus $50 for every car he sells. How many cars will he need to sell this week to earn a total of $700
Alex Ar [27]

Answer:

He would sell 14 cars.

Step-by-step explanation:

Hope this helps

3 0
3 years ago
What is the slope of the line that goes through points(-2,2),and(-4,-2)
Dahasolnce [82]
Slope = y2 - y1/x2 - x1
slope = -2 - 2/-4 - -2
slope = -4/-2
slope = 2
8 0
3 years ago
What is the estimated age of Earth?
Serhud [2]

Answer:

4.543 billion years i think, i apologize if im wrong

Step-by-step explanation:

6 0
3 years ago
Read 2 more answers
Can someone help me with these pls?
mars1129 [50]

Answer: 2420

Step-by-step explanation:

This is a hard multiple choice and multiple task question but im your friend so ill help what you do is multiply 11 and 220 and youll get your answer

Hope this helps!!!  ;)

6 0
3 years ago
Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Star
Doss [256]

Answer: the probability that the critical path for this project will be completed within 210 days is 0.99725

Step-by-step explanation:

Given that;

Work break down is;  

 Time Estimates (days)

Activity  Precedes  Optimistic  Most Likely  Pessimistic  

Start          A,B              -                    -                   -  

A               C,D             44                50                 56  

B               D                45                60                  75  

C               E                42                45                   48  

D               F                31                 40                   49  

E               F                27                36                   39  

F              End            58                70                   82

we know that;

Expected Time = ( Optimistic Time + ( 4 × most likely time) + pessimistic time) / 6

and

Variance = [( pessimistic time - Optimistic time) / 6 ]²

so

ACTIVITY              EXPECTED TIME                                 VARIANCE

A                   (44 + (4 × 50) + 56) / 6 = 50                    ((56 - 44) / 6)² = 4

B                   (45 + (4 × 60) + 75) / 6 = 60                    ((75 - 45) / 6)² = 25

C                  (42 + (4 × 45) + 48) / 6 = 45                    ((48 - 42) / 6)² = 1

D                   (31 + (4 * 40) + 49) / 6 = 40                     ((49 - 31) / 6)² = 9

E                   (27 + (4 * 36) + 39) / 6 = 35                     ((39 - 27) / 6)² = 4

F                   (58 + (4 * 70) + 82) / 6 = 70                     ((82 - 58) / 6)² = 16

ACTIVITY     DURATION      ES        EF        LS        LF        SLACK

A                   50                      0        50         0         50            0

B                   60                      0        60        30        90           30

C                   45                     50       95        50        95            0

D                   40                     60      100        90       130          30

E                    35                    95       130        95       130           0

F                    70                    130     200       130      200           0

FORWARD PASS:

ES = MAXIMUM EF OF ALL PREDECESSOR ACTIVITIES; 0 IF NO PREDECESSORS ARE PRESENT.

EF = ES + DURATION OF THE ACTIVITY.

CRITICAL PATH = PATH WITH THE LONGEST COMBINED DURATION VALUE AND 0 SLACK.

CRITICAL PATH = ACEF

DURATION OF PROJECT = 200

Now the probability

VARIANCE OF CRITICAL PATH = SIGMA(VARIANCE OF THE CRITICAL PATH) = 25

STANDARD DEVIATION OF CRITICAL PATH = SQRT(VARIANCE OF CRITICAL PATH) = 5

EXPECTED TIME = DURATION OF THE PROJECT = CRITICAL PATH = 200

DUE TIME = 210

Z = (DUE TIME - EXPECTED TIME) / STANDARD DEVIATION OF CRITICAL PATH)

Z = (210 - 200) / 5 = 2

Now form the Normal Distribution Table;

Z = 0.99725

Therefore, the probability that the critical path for this project will be completed within 210 days is 0.99725

3 0
3 years ago
Other questions:
  • Izzie recently took a math test where each correct answer (a) on the main part of the test was worth 8.3 points. She also correc
    5·1 answer
  • What is 635/72=-5/2(-11/4+x)
    14·1 answer
  • In basketball tournament Dimitri averaged 12.375 rebounds per game what is 12.375 written in expanded form how is it written wit
    6·2 answers
  • If 8 men took 10hrs to build a wall how long will it take 4 men to build the same wall
    9·1 answer
  • Between two integers does 42lie on the number line? I really need this answered!!
    13·2 answers
  • (please help) List the three lowest numbers that have the following characteristics. Work must be shown. 60 is a multiple of the
    5·1 answer
  • HELP I NEED HELP ASAP
    6·1 answer
  • The cost, d(x), for a taxi ride is given by c(x) 2x + 3.00, where x is the
    14·2 answers
  • The owner of a candle store purchases his candies from a local distributor. The graph below shows the relationship between n, th
    14·2 answers
  • 9w = -54<br> what does w =
    7·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!