Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Isn’t it 1 / 1 ?or something like that is positive for sure
It should be around 24.56 i rounded tho