Answer:
$1,002,000
Explanation:
The costs incurred on the share for share exchange include the fair value per share ,issue costs,direct cost as well as contingent consideration(consideration based on the acquired business performance.
However,the costs eligible to be recorded as investment upon acquisition are the fair value per share and the contingent obligation as shown below:
Fair value (entire shares) $50*20,000=$1,000,000
fair value of potential obligation =$2000
total value of investment $1,002,000
The issue costs and direct should be expensed immediately.
Answer:
mack tax basis in prairee on 31 december = 307000
correct option is a. $307,000
Explanation:
given data
tax basis = $320,000
net business income = $152,000
services rendered = $4,000
distribution = $50,000
solution
we know allocated income is here
allocated income = net business income - guaranteed payment
allocated income = 152000 - 4000
allocated income = 148000
so
mack share of net income is 25 % of allocated income
mack share of net income = 37000
so
mack tax basis in prairee on 31 december = 320000 + 37000 - 50000
mack tax basis in prairee on 31 december = 307000
Answer:
d.
Explanation:
Based on the information provided within the question it can be said that the correct steps that are used by the FASB in developing GAAP (generally accepted accounting principles) would be the following: issuing a discussion memorandum, issuing an exposure draft, and issuing a statement of principle. This collection of accounting rules was then adopted by the U.S. Securities and Exchange Commission.
Answer:
true
Explanation:
Operating profit is referred to as the profit gained by the corporation in business. it is calculated by subtracting all expenses from the total profit over the given period.
it is considered to be the best way to determine how management tactics are helpful or beneficial for the organization. it helps to decide on the working policy for future goals.
Answer:
$33.33
Explanation:
The computation of the predetermined overhead rate is shown below: In this question, we have to apply the formula that is presented below:
Predetermined overhead rate = (Total estimated overhead) ÷ (estimated direct labor-hours)
= $2,500,000 ÷ 75,000 direct labors hours
= $33.33
Simply we divide the anticipates total overhead by the anticipated direct labor hours