Answer:
235 workers
Step-by-step explanation:
Factory operates on a standard work week shift for 5 days = 8 hours per day
In one week working hours are = 8 × 5 = 40 hours.
Company has an order for 7,500 new cars to be delivered in one week.
One car requires time to be fitted with a new hood ornament that requires to install = 1 hour and 15 minutes ( 1.25 hours )
In 40 hours (one week) cars will install with one worker = = 32 cars
To fulfill the order of 7,500 cars, Company needs workers = 7,500 ÷ 32 = 234.375 ≈ 235 workers.
235 workers must be assigned this job to meet the deadline.