Can an expert help with this

Mathematics
1 answer:
SVEN [57.7K]3 years ago
7 0

The formula of an area of a circle:

A_O=\pi r^2

We have

r = 1.8 m

π ≈ 3.14

Substitute:

A_O=\pi\cdot1.8^2=3.24\pi\ m^2\approx3.24\cdot3.14=10.1736\ m^2\approx10.17\ m^2

You might be interested in
M5_A3. The expected project completion time for the construction of a pressure vessel is 18 monthsand the project variance is 7.
snow_tiger [21]

Answer:

a) 0.3520

b) 0.9884

c) 0.1292

d) 0.1292

e) 0.7648

Step-by-step explanation:

Problems of normally distributed samples can be solved using the z-score formula.

In a set with mean \mu and standard deviation \sigma, the zscore of a measure X is given by

Z = \frac{X - \mu}{\sigma}

After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X.

In this problem, we have that:

The expected project completion time for the construction of a pressure vessel is 18 months. So \mu = 18.

And the project variance is 7. The standard deviation is the square root of the variance, so \sigma = \sqrt{7}.

a) What is the probability that the project will require at least 19 months?

The pvalue of the zscore of X = 19 is the probability that the project will require less than 19 months. So the probability that the project will require at least 19 months is the subtraction of 1 by this pvalue.

Z = \frac{X - \mu}{\sigma}

Z = \frac{19 - 18}{\sqrt{7}}

Z = 0.38

The pvalue of Z = 0.38 is 0.6480.

So the probability that the project will require at least 19 months is 1 - 0.6480 = 0.3520.

b) What is the probability that the project will be completed within 24 months?

This is the pvalue of the zscore of X = 24.

Z = \frac{X - \mu}{\sigma}

Z = \frac{24 - 18}{\sqrt{7}}

Z = 2.27

The pvalue of Z = 2.27 is .9884. This means that the probability that the project will be completed within 24 months is .9884.

c) What is the probability that the project will require at least 21 months?

Same logic as a). We find the pvalue of the zscore of X = 21, then we subtract 1 by this value.

Z = \frac{X - \mu}{\sigma}

Z = \frac{21 - 18}{\sqrt{7}}

Z = 1.13

The pvalue of Z = 1.13 is 0.8708.

So the probability that the project will require at least 21 months is 1 - 0.8708 = 0.1292.

d) What is the probability that the project will be completed within 15 months?

Same logic as b). This is the pvalue of the zscore of X = 15.

Z = \frac{X - \mu}{\sigma}

Z = \frac{15 - 18}{\sqrt{7}}

Z = -1.13

The pvalue of Z = -1.13 is .1292. This means that the probability that the project will be completed within 15 months is .1292.

e) What is the probability that the project will take between 16 and 24 months to complete?

This is the pvalue of Z = 24 subtract by the pvalue of Z = 16.

In b), we found that the pvalue of Z = 24 is .9884

Now we find the pvalue of Z = 16

Z = \frac{X - \mu}{\sigma}

Z = \frac{16 - 18}{\sqrt{7}}

Z = -0.76

The pvalue of Z = -0.76 is 0.2236

So the probability that the project will take between 16 and 24 months to complete is 0.9884 - 0.2236 = 0.7648

8 0
4 years ago
Is algebra.
photoshop1234 [79]
Quadratic trinomals are in the form of x^2+bx+c
You need to find the factors of c that add up to b.
So the first question x^2+5x-14
You are looking for the factors (multiply) of -14 that add up to 5
You need to do the same for the next one. Factors of 3 that add up to -4
Those factors would be -3 and -1
That makes the factors (x-1)(x-3)
8 0
3 years ago
Can somebody help please #asap help w number 8
VLD [36.1K]

Answer:

y=4x bc each one is 4 so for one box it cost $4

4 0
3 years ago
Read 2 more answers
PLEASE HELP!!!!!!!!! ​
Ksju [112]

Answer:

C. Graph C :)

Step-by-step explanation:

6 0
3 years ago
Graph y=3/4x+2.please
iren [92.7K]
There
That’s the table of values and the graph itself

6 0
2 years ago
Other questions:
  • 12 over 65.4 = 24 over x (12/65.4=24/x) What is x?
    13·1 answer
  • I REALLY NEED HELP WITH MY CALC CORRECTIONS. THIS IS THE THIRD TIME IVE POSTED THIS. I NEED HELP ASAP PLS!! I HATE CALC 1
    10·1 answer
  • Fico is a credit score. true false user: collin has a credit card bill of $3,000. he makes only the minimum payment and is alway
    6·2 answers
  • A right triangle has legs that are 10.1 inches and 12.2 inches long. what is the approximate length of the hypotenuse?
    12·2 answers
  • 4(-x+4)=12 <br> With steps
    13·2 answers
  • An obtuse angle in the figure is
    7·2 answers
  • A donut shop made 32 chocolate donuts one morning. The chocolate donuts were 40% of the total number of donuts made that morning
    9·1 answer
  • Andrew bought a bottle of water for $1.75, two books for $10.50 each, and a slice of pizza for $3.75. At the end of the day, he
    12·1 answer
  • Hey guys i need some help :)
    12·1 answer
  • The temperature was +12 degrees at midday. By evening, the temperature was -20 degrees. What was temperature change?
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!