Hi there
units were transferred to the finished goods inventory during february
5,200+740−440
=5,500...answer
Good luck!
I think is 475848 because I just timed by 48 so I got 475848
Answer:
$54.35
Explanation:
The computation of the price per share of the common stock is shown below:
= Next year dividend ÷ (Required rate of return - growth rate)
where,
Next year dividend is
= $3.23 + $3.23 × 4.2%
= $3.23 + 0.13566
= $3.37
And, the other items would remain the same
So, the price per share is
= $3.37 ÷ (10.4% - 4.2%)
= $3.37 ÷ 6.2%
= $54.35
A functional/hybrid resume would be more suitable for this situation.
Chronological order is normally most supportive when itemizing work understanding, so a potential boss can see where you worked and for to what extent, so it isn't as simple to apply chronological order to your group inclusion or broad preparing.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.