Answer:
The correct answer to the following question will be "The capacity to work without reference to the data that would be contained in each bundle".
Explanation:
- The Layer network governs the activity of the subnet. The main objective of this layer would be to transport data over multiple links from source to destination. When two computers are linked to the same cable, see no need for the network layer.
- The role of this layer protocols defines the configuration and handling of packets used to transfer information from one to another host.
- The main purpose of this layer is to allow multiple channels to be intertwined. This is achieved by sending packets to network adapters that depend on algorithms to identify the best directions for the information to move. Such routes are referred to as computer circuits.
Therefore, it would be the right answer.
mbly code to implement the y=(x1+x2)*(x3+x4) expression on 2-address machine, and then display the value of y on the screen. Assume that the values of the variables are known. Hence, do not worry about their values in your code.
The assembly instructions that are available in this machine are the following:
Load b, a Load the value of a to b
Add b, a Add the value of a to the value of b and pla
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
Spell-check feature is the one that auto corrects any misspelled words
Ok if lets say a young child at the age of like 6-7 was allowed to play grand theft auto by his/her parents maybe the child would understand incorrectly and start doing what the people do in the game this may cause to serious trouble jail time or even death. In this case dont let your kids play underrated games or watch underrated movies.
Hope that helped you understand more.