Answer: ($203)
Explanation:
The company’s 2010 change in net working capital will be calculated thus:
Net working capital = current assets - current liabilities
For 2009, net working capital will be:
= $2,584 - $1,191
= $1393.
For 2010, net working capital will be:
= $2,644 - $1,048
= $1596
Change in net working capital will be:
= $1393 - $1596
= ($203)
Answer:
Malcolm is a professional writer. He has already published many best-sellers. One of his friends expressed interest in knowing more about his writing process, so Malcolm showed his friend a few of his first drafts. The friend observed that the drafts were nothing like the final book, and the writing seemed amateurish compared to Malcolm's published work. When asked about it, Malcolm said that it was the normal way of things. In this scenario, the following is the reason of this:
A) Malcolm would have revised his work many times before he was satisfied with it.
Explanation:
- The option A is best reason because generally a writer doesn't break his or her flow while writing and that is what Malcolm would have done. After, he would have revised his work many times until he was satisfied.
- The option B is not correct as it is not possible to change the book of a writer entirely by the publishing company.
- The option C is also incorrect as the drafts were not long and cohesive because his friend found the draft amateurish but not perfect.
- The option D is incorrect as it is not true that writers only create first draft and other people produce all other subsequent drafts.
Answer:
NPV = 138,347.55
Explanation:
<em>Net Present Value (NPV) : This is one of the techniques available to evaluate the feasibility of an investment project. The NPV of a project is the difference between the present value of the cash inflows and the cash outflows of the project.</em>
We sahall compute theNPV of this project by discounting the appropriate cash flows as follows:
<em>Prevent Value of operating cash flow</em>
PV =A× (1- (1+r)^(-n))/r
A- 23,900, r - 12%, n- 5
PV = $23,900 × (1- (1.12)^(-5))/0.05
=206,769.963
<em>PV of Working Capital recouped</em>
PV = 5600× 1.12^(-5)
= 3,177.59
NPV = initial cost + working capital + Present Value of working capital recouped + PV of operating cash inflow
NPV = (66,000) + (5600) + 3,177.59 + 206,769.96
NPV = 138,347.55
Answer:
correct option is b. job-order cost sheet
Explanation:
A job order cost sheet is subsidiary to work in process
because job-order cost sheet are the documents that is use for record the manufacture cost.
and all necessary and important detail of cost & job is written in job cost sheet
and it is also accounting record of the company
so here given that primary document for accumulate all cost related to a particular task
so correct option is b. job-order cost sheet
Answer:
$4620
Explanation:
Activity method based on hours worked = (hours worked that year / total hours of the machine) x (Cost of asset - Salvage value)
33,000 / 2000,000) x ($35,000 - $7000) = $4620