Answer:
The range of possible transfer is $ 3.25 to $ 3.50
Explanation:
Data provided:
The purchasing cost of the transistor = $ 3.50
The total number of transistors needed = 8,000
The production cost of the transistor = $ 4.00
The included variable cost = $ 3.25
The included fixed cost = $ 0.75
Now,
the fixed cost cannot be altered, thus it will be there
hence,
the variable cost will be the factor that will evaluate the decision i.e $ 3.25
therefore, the <u>range of possible transfer is $ 3.25 to $ 3.50</u>
Answer:
Explanation:
X - number of units sold
Total cost for production = 1,500,000 + 1600X
Total cost for purchasing = 2000X
a. For 4000 units sold
Total cost for production = 1,500,000 + 1600 * 4000 = $7,900,000
Total cost for purchasing = 2000* 4000 = $8,000,000
In this case producing is cheaper. Therefore, it is better to produce
b. Y - break-even point
Then : 1,500,000 + 1600 * Y = 2000* Y
So 1,500,000 = 400 Y
Y = 3750
At №of units less than 3750 purchasing will be the better option
And above 3750 producing will be the better option
Answer:
B. through negotiations between the parties involved.
Explanation:
- correct answer is through negotiations between the parties involved because According to Coase theory, priority rights are best defined by negotiation between the parties involved and there is no transaction cost in negotiations.
- The Coase theory states that when transaction costs are low, both parties can negotiate and reach an effective outcome in the presence of an outsider.
Premium is not included in all contracts.
Offer is very important, time requirements is also a must in a contract, consideration is also stated in the contracts, but premium is not included in the contract.
Answer: C. 50%
Explanation:
From the above question, If conversion costs are added evenly throughout the production process and the unit have made it 50% of the way through the production process then the percentage completion for conversion costs is 50%