sally can paint a room in 7 hours while it taks steve 9hours to finsh the same room. how ling will it take them to paint if they
worked together?
2 answers:
Sally alone can paint the room in 7 hours.
In 7 hours Sally alone does the job.
In 1 hour Sally would do (1/7) of the job.
Steve can paint it alone in 9 hours.
In 9 hours Steve alone does the job.
In 1 hour Steve would do (1/9) of the job.
Both working together in 1 hour would do: (1/7) + (1/9).
(1/7)*(9/9) + (1/9)*(7/7) = 9/63 + 7/63 = (9 + 7) / 63 = 16/63
In 1 hour both will have done (16/63) of the job.
16/63 of the job will be done in 1 hour by both.
Therefore a 1 whole fraction of the job will be done in: 1 hour ÷ 16/63
= 1 hour × 63/16
= 63/16 hours = 3.9375 hours
It would take both 63/16 hours or 3.9375 hours.
How much part can sally paint in an hour ?
a ÷ 7 = a/7
And what about Steve ?
a ÷ 9 = a/9
Where, a is the total area of the room.
So, let the time taken by both of them to paint the room together be 't'
So,
t(a/7 + a/9) = a
t(9a/63 + 7a/63) = a
t(16a/63) = a
t = 63/16 ≈ 4 hr
You might be interested in
Answer:
12 girls
Step-by-step explanation:
16 divided by 4 is 4
Since the ratio is 4:3, that means that for every 4 boys, there are three girls.
3 x 4 is 12
Your answer is 12 girls.
Answer:
0.23
Step-by-step explanation:
less than 0.24 and greater than 0.007
Answer: the first one
Step-by-step explanation: the number is 42 45 45 46 and 48 are all close together while the number 16 is off to the whole other side
- 6/2c is the correct solution
collect like terms : 3cx - cx = 2cx
hence 2cx = - 6
dividing both sides by 2c gives x = - 6/2c
C is 23 because if you get all rhe numbers and measure thats your answer. I think i might be wrong. if I am then sorry