Answer:
A and D
Explanation:
Your top leader coordinates the activities of functional departments, like the Marketing and Sales department, and customer groups, like Small Business Accounts division.
One matrix boss is in charge of the Small Business Accounts division.
In an organization that has a matrix structure, one matrix boss oversees one side of the matrix, either a functional area (in this case Marketing & Sales) or a division (in this case the Small Business Accounts division).
Top leader is used to describe the manager that coordinates the entire matrix, in this case, both the Small Business Accounts division and the Marketing and Sales department. This manager must resolve competing demands between the two sides of the matrix.
Answer:
We need 11 deposits of $ 5,268.735 per year to achieve our desired retirement plant.
Explanation:
Present value of the retirement plan in 11 years:
C 14,000.00
time 16
rate 0.12
PV $97,635.8061
We need to get that amount in 11 year at 10% annual rate:
FV $97,635.8061
time 11
rate 0.1
C $ 5,268.735
Answer:
Goodwill is calculated as A. The amount paid to purchase a business in excess of the market value of its net assets.
Explanation:
Goodwill is the quantification of the value of the name or reputation of a business. It is an intangible asset for the business that arises and is recorded as part of a business's value when it is sold. Goodwill is the additional amount paid by the buyer in excess of the amount that a business's tangible net assets are worth. Thus, goodwill can be calculated as the amount paid in to purchase a business in excess of the market value of its net assets.
For example, If a business is purchased for $100 whose net assets, which are Total assets less total liabilities, are worth $80. Then the goodwill is the $20 that is the difference of the amount paid to purchase the business and the value of its net assets.
<span>Partnership. They both together running the business with efforts and money so this action called partnership. Partnership action don't have to equal it can be 80%-20% or 40%-60% or anything. Not only persons have to be two it can be three or four or anything more than one.</span>
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186