Answer:
y = (C -0.99n)/48
Step-by-step explanation:
Undo what is done to y, in the reverse order. We have y multiplied by 48 then added to 0.99n. So, we must add the opposite of 0.99n and multiply that result by the reciprocal of 48.
C = 48y + 0.99n . . . . . . given
C - 0.99n = 48y . . . . . . add -0.99n
(C -0.99n)/48 = y . . . . . multiply by 1/48
Answer:
I dont understand the qustion? did you answer it?
Step-by-step explanation:
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
Then let Cody attend the fall festival!!
Step-by-step explanation: